Roadmap

Iteration 1

RSF port, deeper gradebook integration, minimal functionality

  • Completed in January, 2008

Iteration 2

Parity with legacy assignments tool functionality, site-to-site import for migration, but without significant design changes

  • Feature Freeze March 7, 2008.
  • QA through April 11

Iteration 3

Refinement for Production

  • Design completed by April 11, 2008
  • Production deployment at IU June 21

Iteration 4

Final cleanup of Iteration 3 design

  • whatever polish needs to be applied between June and August

Iteration 5

Redesign of User Experience

  • Using a JSON approach for rapid UI development
  • UX goals: simplicity of screens, clarity of workflow, design for large class tasks as well as small
  • Will work through several iterations of usability testing in May
  • Targeting deployment at Georgia Tech in August

Deployment at IU

  • Iteration 3 to be piloted in June, 2008
  • Full production in August

Deployment at Georgia Tech

  • Iteration 5 to be piloted in July, 2008
  • Full production in August